Greetings Polk Street Community Member,

This is an excerpt from the official DPW Polk Streetscape Project page.

Click here to view all the latest construction information for the Polk Streetscape Project. You may sign up there for important updates delivered directly to your email inbox.

REMINDER: San Francisco Water Department crews will be performing work after normal work hours the evening of Monday 09/11/2017 at the intersections of Polk and Filbert from 8 PM to 11:55 PM and at Polk and Chestnut from 10 PM to 2 AM. Crews will be working to complete water service connection work. To report any water related issues or emergencies, please call 3-1-1 or call 415-550-4956.

Project Activity Summary

Bus pad installation work at the SW corner of Polk and North Point, along with other concrete flat-work has been completed for segment 5, along with water connection work at Polk and Bay in segment 4.

Week of September 11, 2017
Crews will continue with concrete work in segment 4, which includes: curb ramp, street base and bus pad installation work at various locations along the segment limits. Crews will continue with 33″ sewer main installation work on Polk between Pine and California in segment 3. Segment 5 roadway paving is scheduled to occur this week between September 12-15, 2017, on North Point Street between Van Ness and Larkin Street and on Polk between Beach and Bay streets. Bus pad installation work will begin at the intersections of Polk and Lombard and Polk and Francisco from September 11 to September 13, followed by a 10 day curing period.

Week of September 18, 2017
Crews plan to wrap up with sewer main installation work on Polk between Pine and California and will continue with curb ramp work at various intersections in segment 4.
Construction Schedule Update

Construction for the Polk Streetscape Project is anticipated to be completed in six segments over a 24 month period. Construction in segments 5, 4 & 3 are currently underway, with work in segments 2, 1 and 6 pending.

Anticipated construction schedule for Segment 5:
October 2016 – September 2017

Anticipated construction schedule for Segment 4:
November 2016 – November 2017

Anticipated construction schedule for Segment 3:
August 2017 – April 2018

Anticipated construction schedule for Segment 2:
September 2017 – June 2018

Anticipated construction schedule for Segment 1:
March 2018 – July 2018

Anticipated construction schedule for Segment 6:
May 2018 – August 2018

*Please note that the construction schedule is subject to change due to rain, equipment breakdown, and/or unforeseen field conditions. Please see posted “No Parking” barricade signs for exact parking restrictions. Parking restrictions may vary per block. 