Construction Forecast: Rocks and Gravel, with a Chance of Fog

Crews performing archaeological potholing on Van Ness Avenue near Market Street to determine the presence of cultural materials in the project area. Photo courtesy of SFMTA.

[We are passing along some information from SFMTA about the Van Ness Corridor construction that is happening right now.]

Construction Forecast: August 21- September 1, 2017

The following Van Ness Improvement Project construction forecast is subject to change due to weather or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

Work is planned over the next month to create two construction zones: one southbound on Van Ness Avenue from Sutter to McAllister streets, and another northbound from Jackson to Lombard streets. These work areas will be approximately five feet from the building line to approximately the center of the roadway.

To make space for these construction zones, the following changes will occur:

  • Blue curb parking for people with disabilities and loading zones will be temporarily relocated beginning Tuesday, August 22.
  • Bus stop located on southbound Van Ness at McAllister will be reconfigured beginning Wednesday, August 23.
  • Southbound traffic lanes are expected to shift Monday, August 28
    Parking is expected to be temporarily removed for construction southbound Van Ness between Sutter and McAllister beginning Monday, August 28.
  • Northbound traffic lanes are expected to shift Tuesday, September 5.
  • Parking is expected to be temporarily removed for construction on northbound Van Ness between Jackson and Lombard beginning Tuesday, September 5.
  • Project staff is reaching out directly to businesses and residents on blocks that are impacted by these changes. See the full schedule of expected activities below.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Monday, August 21: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Tuesday, August 22: Blue curb parking for people with disabilities and loading zones will begin being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Wednesday, August 23, through Friday, August 25: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Monday, August 28: Southbound traffic lanes are expected to shift toward the center of the roadway to create a construction work zone on the southbound side of Van Ness Avenue from McAllister to Sutter streets. The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Tuesday, August 29: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones begin being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Wednesday, August 30: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will return near to its original location on the southwest corner. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Thursday, August 31, through Friday, September 1: Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Related Projects

Polk Streetscape Project

An artist’s rendering depicts Polk Street near Geary Street after the Polk Streetscape Project is completed.

Polk Streetscape Project Construction Activity Update

Crews will continue to wrap up concrete work on North Point Street, continuing with sidewalk work and will begin curb ramp work at the southeast corner of Polk and North Point streets. Sewer work will continue on Polk between Pine and California. Sewer work from Pine to Vallejo is anticipated to continue through mid-September 2017.

Find out more and sign up for project updates at sfpublicworks.org/polk.

Supporting Business on Van Ness

Van Ness businesses encouraged to take Open for Business Survey

To provide direct and customized marketing support to Van Ness corridor businesses through construction, the San Francisco Office of Economic and Workforce Development (OEWD) has created the Open for Business program.

To tailor this construction support program to meet the unique needs of local businesses along the corridor, Van Ness merchants are being asked to take a five-minute survey. The survey can be found online at surveymonkey.com/r/VanNessOFB. If you have questions about the program or how you can get involved, email [email protected].

Be a voice for business on Van Ness!

The SFMTA is seeking applications to fill vacated seats on the Van Ness Business Advisory Committee.

The Van Ness Business Advisory Committee is made up of representatives from a diverse cross-section of Van Ness project corridor businesses. Members act as the voice of the community and provide recommendations and advice on how staff can best work with local businesses during construction of the Van Ness Improvement Project to bring out the character that has made this vital thoroughfare one of the city’s grand avenues.

The Van Ness Business Advisory Committee meets monthly on third Thursdays and operates independently from the Van Ness Bus Rapid Transit Community Advisory Committee, focusing on the impact the project has on local businesses.

People who represent businesses on Van Ness corridor and the neighboring community are encouraged to apply. Note that applications are due no later than Thursday, August 31, 2017.

If you have any questions, contact [email protected] or 415-646-2310.

Contact Us

Please contact us if you have any questions or concerns at 415-646-2310 or at [email protected].

Community Drop-In Office Hours 

Have a question about construction or the Van Ness Improvement Project? Stop by our Construction Office at 180 Redwood Street, 3rd Floor (near Van Ness and Golden Gate) to get assistance from project staff during our Community Drop-In Office Hours on Tuesdays, 2:00-4:00 p.m., and Fridays 10:00 a.m.-12:00 p.m. (excluding holidays).

###