Polk Streetscape Project Updates

Courtesy of SF Public Works.

As you may know, SF Public Works is working on a major upgrade to the entire Lower Polk Corridor. More information is located here: http://www.sfpublicworks.org/project/polk-streetscape-project.

In addition, SFPW also has a free email newsletter that you can subscribe to. It contains regular updates about the Polk Streetscape Project. To sign up, just click here and type in your name and email. Here is some information from that newsletter:

Week of June 26, 2017

Contractor will wrap up side sewer replacement work on Polk Street from Francisco to Union. Crews will continue to assist SF Water Dept work on North Point Street. Segment 4 roadway street base work will continue over areas of sewer work, additional roadway work will occur after all underground work is complete. Contractor is also mobilizing an additional crew which will begin concrete work (MUNI bus pad, parking strip, street base) on North Point Street in segment 5.

Week of July 03, 2017

Crews will NOT be working Monday July 3rd or Tuesday, July 4th. Crews will resume work on Wednesday, July 5th. Crews will continue concrete work on North Point Street, segment 4 restoration and possibly get into segment 3 at the Broadway and Pacific intersections.

Anticipated construction schedule for Segment 5:

  • Water work: 04/2017- 06/2017
  • Concrete Flatwork: 07/2017
  • Final Grind & Pave: 07/2017

Anticipated construction schedule for Segment 4:

  • Sewer work: 11/2016 – 06/2017
  • Water work: 03/2017 – 011/2017
  • Concrete Flatwork: 07/2017 – 10/2017
  • Electrical work: 04/2017 – 10/2017
  • Final Grind & Pave: 10/2017

Read the entire SF Public Works Polk Streetscape Project email newsletter here. . . and visit the main project webpage here. Don’t forget to sign up here.