Polk Streetscape Project Update

Polk Streetscape Project Update

Here is the latest construction information for the Polk Streetscape Project:
 
Week of October 22, 2018
Crews will continue sidewalk and curb ramp work on Austin Street between Polk and Van Ness Avenue and will continue landscape irrigation and tree planting work on Fern between Polk and Larkin Street. Remaining work on Fern includes: street light installation, roadway paving and decorative asphalt stamping work. Electrical and landscaping crews will continue street light/traffic signal and tree planting activity at other various locations along Polk Street. 
 
Week of October 29, 2018
Crews will wrap up sidewalk and curb work on Austin Street between Polk and Van Ness Avenue and will begin street base repair work. Remaining work on Austin includes: street light installation, tree planting and final roadway paving.
 
On Tuesday, 10/31/18 and on Wednesday, 11/1/18, crews will perform the next phase of grinding and paving activity on Polk Street, between Golden Gate Ave. and McAllister Street, on Redwood Street, between Polk and Van Ness and on Willow Street, between Polk and Larkin streets. Electrical and landscaping crews will continue to work on street light/traffic signal and tree planting activity at various locations along Polk Street. 
 
Week of November 5, 2018
Crews will work to complete street base repair work on Austin. Electrical and landscaping crews will continue to work on street light/traffic signal and tree planting activity at various locations along Polk Street. 
 
Upcoming Paving Activity
The final phase of paving activity is anticipated to occur in Mid-November 2018 onl Fern between Polk and Larkin and on Austin between Polk and Van Ness Avenue. Additional paving details will be shared as we get closer to these dates and paving schedules are finalized. 
 
For the latest project updates and information regarding the Polk Streetscape Project, or to sign up for email updates, please visit www.sfpublicworks.org/polk. 
 
Upcoming traffic changes
With the upcoming Polk Street paving work, SFMTA is implementing new striping of travel lanes with new improved bikeway designs. Parking and loading changes will occur with the new striping, including the removal of all parking on the east side of Polk Street between Pine Street and McAllister Street and some removal of parking on the west side of Polk Street with improved commercial and passenger loading spaces to better accommodate the area’s demand. See www.sfmta.com/polk for more information.
 
SFMTA legislated parking and loading changes for Polk Street and these changes will be implemented after final paving is completed for each segment. The parking and loading changes to the Polk side streets north of California Street have been implemented and the remainder of side streets changes will occur later this fall. To see the final parking and loading changes on Polk Street and the cross-streets, please see the final traffic striping plan here.

Polk Streetscape Project – Things to Know:  

General work hours are Monday-Friday 8AM to 5PM.

Contractor Contact
 
Shane McCarthy, Project Engineer / 24/7 Emergency Phone: 415-661-6902 / Email: [email protected]
 
San Francisco Public Works Contact
 
Coma Te, Public Affairs Officer / Phone: 415-558-5283 / Email: [email protected]. SFDPW is working closely with partner agencies to coordinate construction activity with other projects in the area, such as the Van Ness Improvement Project with SFMTA (www.sfmta.com/vanness). 
 